Home / Frost Depth in Toronto: What It Means for Footings

Frost Depth in Toronto: What It Means for Footings

Reviewed October 2026 · Toronto & the GTA

Typical cost1.2 mbelow finished grade to the underside of the footing (Part 9, 2024 OBC)
ResultsEngineer sets the designrush available
Best forWalkouts, additions, crawl spaces and winter starts

The frost depth figure Ontario builders work to is 1.2 metres, about 4 feet: under Part 9 of the 2024 Ontario Building Code, a footing that is not on sound bedrock is taken at least 1.2 m below finished grade, measured to the underside of the footing. In Toronto it matters for anything outside the heated house, like a walkout stair, a porch or an addition, and for any excavation left open in cold weather.

That figure is a design minimum, not a measurement of how far the ground froze last winter. It is also not the whole story for a basement. A house's own footings already sit far below it, and underpinning takes them deeper still. Where frost becomes a real design question on an underpinning job is at the edges: the stairwell of a new walkout, a shallow footing under a porch or a rear addition, a crawl space being dug out, and the bottom of a trench that is open in January. This page goes through each of those, with the rules and the people who apply them.

We coordinate underpinning projects and the engineering and permits they need. We do not perform structural engineering, and the depth of any footing on your house is set by the engineer's design, not by this page.

Rather just talk?

(289) 207-6470

Tell us your basement perimeter and current ceiling height and we can give you a realistic range on the call.

  • A firm, itemized price up front
  • Permits and engineering in the number
  • The real timeline, honestly
Call now

Get a real range

Not a brochure. Tell us the basics and we will come back with numbers that reflect your actual foundation.

No obligation. Your details go only to our Toronto team.

Where the 1.2 metre figure comes from

The rule lives in Part 9 of the Ontario Building Code, in Subsections 9.12.1 and 9.12.2, which cover excavation and the depth of foundations. The 2024 code applies across the province, so the same rule governs a footing in Scarborough, Etobicoke or Ottawa.

Ontario building departments that publish plain-language guides to Part 9 state it the same way. Carleton Place's Building Code Guideline for Part 9 decks, issued April 1, 2025 for the 2024 code, says that where foundations are not supported on sound bedrock they need "a minimum depth of 1.2 m (47 1/4") below grade, measured from finished grade down to the underside of footing." The same guideline sets out the two ways around it:

  • Sound bedrock. A footing bearing on sound bedrock that is not susceptible to frost movement can sit on the rock at any depth. That is rare under a Toronto house.
  • Designed frost protection. Where the depth or the bedrock cannot be achieved, alternative frost protection, such as insulation, has to be designed by a qualified professional.

Toronto's own guide for decks and porches does not print a number, but it asks every permit drawing to show "footing size, spacing, depth, height above grade and frost protection details." In other words, the City checks the frost protection on the drawings, and the designer has to show how it is achieved.

The point

Two things people get wrong: the 1.2 m is measured to the bottom of the footing, not the top, and it is measured from the finished grade, so regrading a yard after the footings are in can quietly make them too shallow.

Why the ground freezing matters at all

Frost damage is not about cold concrete. It is about wet soil. The City of Markham's Builder Tip No. 47, updated to the 2024 code, explains the mechanism in a few lines:

  • Water expands about 10 percent by volume when it freezes.
  • The real heaving comes from ice lenses, which form when water is drawn from unfrozen soil into the frost zone and freezes there.
  • In Ontario the ground can freeze to a depth of several feet in winter, and certain soils are more prone to heave than others, depending on the soil type, the moisture content and how deep the frost goes.

A footing above the frost line can be lifted in winter and dropped unevenly in spring. A footing poured on ground that froze before the concrete went in will settle as that ground thaws. Both show up later as cracks, sticking doors or a stair that pulls away from the house, which is why the code cares about the depth.

Toronto's soils make this more than theory. The City's underpinning guide lists clay or silt soil as one of the conditions that triggers a Professional Engineer's design, and fine-grained soils that hold water are exactly the kind the Builder Tip warns about.

Why your basement footings are not the problem

A typical Toronto basement floor sits several feet below the yard, and the house's footings sit below that. The foundation is also next to a heated space for most of the year. So the frost line is rarely a live question for the main footings of an occupied house, and underpinning only moves them further down: the new footings are poured beneath the old ones, section by section, to lower the floor. Our guide to basement lowering in Toronto explains how far that typically goes and what limits it.

The cases where frost is a genuine design question on a basement project are the ones below.

1. The walkout stairwell

A walkout is a hole cut down beside the house, and that changes the ground in two ways. The stairwell's own footings, under the landing and the side walls, are outside the heated house. And the house's foundation next to the stairwell now has much less soil over it on one side.

That is why a walkout is engineered as more than a door:

  • The landing and stairwell wall footings are taken deep enough to sit below frost, or protected by a designed alternative.
  • They are tied into the underpinning so the entrance and the house do not move separately through a freeze and thaw.
  • The stairwell side walls are retaining walls, holding back soil, water pressure and, in winter, frost.
  • Drainage at the bottom of the stair keeps water from sitting in the soil under the landing, which is the water that would freeze.

A walkout in Toronto typically costs $15,000 to $30,000 on top of underpinning, on our published range, and the frost and retaining work is a large part of why. Our full guide to the basement walkout in Toronto covers the permit, the engineering triggers and the winter details like stair covers and heated drains.

2. Porches, cold cellars, additions and crawl spaces

The house's main foundation is deep. The pieces added to it later often are not. A front porch on piers, a cold cellar under it, a rear addition on a shallower footing or a crawl space under a kitchen extension can each sit much closer to the surface than the original basement.

That matters in two ways on an underpinning job:

  • Where the shallow piece meets the deep house, the two foundations can move differently, and the engineer has to decide how the new underpinning meets the old shallow footing.
  • Digging out a crawl space to full height means building new footings that are both deep enough for the new floor and protected from frost at the outside edge. Our page on the crawl space to basement conversion in Toronto covers what that involves and how it is priced.

There is one more rule from the Carleton Place guideline worth knowing: where new footings are not on sound bedrock, they must not be placed within the angle of repose of an existing foundation. Toronto's underpinning guide uses the same idea for the neighbour's footing, and it is one of the three triggers for a full engineered design. Our page on the underpinning engineer in Toronto explains all three.

3. An open excavation in cold weather

This is the frost rule that catches out winter projects. Ontario Building Code Article 9.12.1.3 says the bottom of an excavation has to be kept from freezing throughout the entire construction period.

Markham's Builder Tip defines the cold weather the rule is worried about as any stretch of more than three consecutive days where the average daily air temperature is below 5 °C and the temperature is not above 10 °C for more than half of any 24 hours. That usually starts in the fall and runs until spring. The tip adds that an open excavation in sub-zero weather can freeze to a significant depth in a few hours, and it recommends that builders consult a geotechnical engineer and prepare a frost protection plan suited to the soil. Insulated blankets are one of the methods it names, and inspectors can ask to see the plan.

For an underpinning job, that splits the work in two:

  • Interior underpinning happens inside a heated basement. Each pit is dug, inspected and poured in a space that stays above freezing, which is a big part of why underpinning goes ahead in any month. Our post on the best time of year to underpin in Toronto covers the scheduling side.
  • Exterior work, like a walkout cut, exterior waterproofing or an addition footing, is an open hole outdoors. In deep winter it needs a protection plan, it is slower, and it is usually better timed for milder weather.

If the house will be empty and unheated during a winter project, raise it with the contractor and the engineer before the first pit is opened. A cold basement changes the frost question for every open section.

4. Concrete poured in winter

The other half of the winter question is the concrete. Concrete placed against frozen ground, or allowed to freeze before it has gained strength, is the failure. Inside a heated basement this is managed by keeping the space warm. Outside, it is managed with heating, insulated blankets and timing, set by the contractor and checked against the engineer's specification.

The practical version for a homeowner is simple: ask how the exterior pours on your job will be protected if they fall in cold weather, and expect a written answer rather than a reassurance. The engineer's site reviews, which the City requires at the first and last stages of every underpinning job, are where that gets checked.

What this means for the cost and the schedule

Frost protection does not carry a separate line on most underpinning quotes. It shows up inside other lines:

  • In the walkout price, through deeper footings, retaining walls and drainage, inside the $15,000 to $30,000 range.
  • In the engineering, at $1,500 to $8,000 on our published range, where the design has to deal with shallow footings, a stairwell or wet clay.
  • In exterior waterproofing, at $3,000 to $12,000, which keeps water away from the footings in the first place.
  • In the schedule, where exterior work in deep winter is slower and sometimes deferred to spring.

The underpinning itself stays at $500 to $750 per linear foot of foundation wall whatever the season. The full breakdown is on our page on underpinning cost in Toronto, and the permit side, including what the drawings must show, is on underpinning permits in Toronto.

Common questions

What is the frost depth in Toronto?

The figure Ontario builders work to is 1.2 metres, about 4 feet. Under Part 9 of the 2024 Ontario Building Code, a footing that is not on sound bedrock is taken at least 1.2 m below finished grade, measured to the underside of the footing, unless a qualified professional designs another form of frost protection.

Is the frost line the same everywhere in Ontario?

The Building Code rule is province-wide. Local soil, drainage and exposure still change how a footing is designed, which is why the engineer or designer, not a map, sets the depth for your project.

Does underpinning go below the frost line?

Yes. The footings of a full basement normally sit below the 1.2 m figure already, and underpinning pours new footings beneath them. The frost questions on an underpinning job are at the edges: walkout stairwells, porches, additions, crawl spaces and open excavations in winter.

Do walkout stair footings need to be below frost?

They need frost protection, because the stairwell is outside the heated house. That usually means footings taken below frost and tied into the underpinning, or a designed alternative such as insulation, set out on the engineer's drawings.

Can you dig footings in winter in Toronto?

Yes, with protection. Ontario Building Code Article 9.12.1.3 requires the bottom of an excavation to be kept from freezing throughout construction. Interior underpinning in a heated basement does this naturally; exterior excavations need a frost protection plan, such as insulated blankets.

Can you pour concrete in winter?

Yes, if it is protected. The risk is concrete placed against frozen ground or allowed to freeze before it gains strength. Inside a heated basement this is routine; outside it needs heating, blankets and timing set by the contractor and checked against the engineer's specification.

Does frost protection change my underpinning quote?

Not as a separate line. It shows up in the walkout price, the engineering and the exterior waterproofing, and in the schedule if exterior work falls in deep winter. The underpinning rate stays at $500 to $750 per linear foot.

Call (289) 207-6470 if you are planning a walkout, an addition or a winter start, or send the details below, and we will tell you which parts of your project the frost rules touch and who should design them.

Rather just talk?

(289) 207-6470

Tell us your basement perimeter and current ceiling height and we can give you a realistic range on the call.

  • A firm, itemized price up front
  • Permits and engineering in the number
  • The real timeline, honestly
Call now

Get a real range

Not a brochure. Tell us the basics and we will come back with numbers that reflect your actual foundation.

No obligation. Your details go only to our Toronto team.

Know the number before you dig.

Tell us your perimeter and current height. We will give you a realistic range, not a brochure.

Call (289) 207-6470
Call nowGet a range