Home / Underpinning Permits in Toronto: What You Actually Need

Underpinning Permits in Toronto: What You Actually Need

Reviewed October 2026 · Toronto & the GTA

Typical cost$2,000 – $3,000permits + engineering combined
Results13-day median approval (2025)rush available
Best forPlanning a realistic project timeline

Underpinning a basement in Toronto requires a building permit, and an engineer is involved on every job: the City requires a Professional Engineer's design and field review where the new footings go below a neighbouring building's footing within the soil's angle of repose (most semis, row houses and tight lots), where underpinning exceeds 1,200 mm of laterally unsupported height, or where the soil is clay or silt, and an engineer's testing and reports at the first and last stages on every underpinning job. What that engineer produces and costs is covered under underpinning engineer in Toronto. On a lot inside a TRCA Regulated Area, a TRCA permit comes before the City permit, and a dig near a protected tree can need a Toronto tree by-law permit as well. Under the City's fee schedule effective January 1, 2026, underpinning is charged at $12.37 per linear metre of wall being underpinned, subject to a minimum building permit fee of $214.79 that applies to all work. (A Markham address is permitted by the City of Markham instead, at its own rates: see basement underpinning in Markham.) For a typical Toronto house that is about $380 for 100 feet of wall and $530 for 140 feet. Engineering adds from about $1,500 for a simple design to $8,000 or more when a neighbour's footing has to be protected; the underpinning cost page breaks that down.

The part that surprises people is not the cost. It is the wait. The Building Code gives the City 10 days to issue or refuse a permit for a house, and yet a slow application can run 6 to 12 weeks; in the City's own data, 18% of 2025 underpinning permits took six weeks or more, while the median was 13 days. Understanding why those two numbers are both true is the single most useful thing on this page, because the gap between them is almost entirely inside your control.

Rather just talk?

(289) 207-6470

Tell us your basement perimeter and current ceiling height and we can give you a realistic range on the call.

  • A firm, itemized price up front
  • Permits and engineering in the number
  • The real timeline, honestly
Call now

Get a real range

Not a brochure. Tell us the basics and we will come back with numbers that reflect your actual foundation.

No obligation. Your details go only to our Toronto team.

Plan the permit timeline before you plan the renovation. A homeowner who books a contractor for next month, without a permit in hand, is booking a delay.

What the permit package must contain

Engineered structural drawings. Prepared and sealed by a professional engineer licensed in Ontario wherever the City requires an engineered design, which on a semi, a row house or a tight lot is almost always. This is a design document, not a contractor sketch. It specifies footing depths, section widths and reinforcement.

The underpinning sequence plan. The specific order in which sections are excavated and poured, so the house is continuously supported. This sequence is the engineering, and it is why the work takes weeks rather than days.

Site and structural details showing existing conditions and proposed depths.

Agreement to staged inspections. Inspections happen during the work at defined stages, not only at completion.

The realistic timeline, end to end

Stage Typical duration
Engineer site visit and drawings 1 - 3 weeks
Permit application review by the City 1 - 6 weeks (median 13 days in 2025; 18% took 6+ weeks)
Underpinning work on site 4 - 6 weeks
Slab cure before finishing 1 - 2 weeks
Total, first call to finished basement 3 - 6 months

Most quotes describe only the 4-6 week middle row. That is not dishonest, it is just the part the contractor controls, but it is why homeowners are repeatedly caught out by the real calendar.

The 10-day rule, and why some permits still take three months

Ontario's Building Code sets a review window for a complete permit application. The Province's own guidance puts it plainly: the timeframe on a permit application for a house is 10 days, rising to 30 days for something complex like a hospital. Within that window the municipality must either issue the permit or refuse it and give its reasons.

So why does anyone wait three months?

Because the clock only runs on a complete application, and almost nobody submits one the first time. The 10 days is not a queue position. It is a review period that begins when your application meets the criteria set out in the Code, and an application that is missing a drawing, a calculation, or a signature has not started the clock at all. Every round of "please resubmit with X" puts you back at the start.

That reframes the whole problem. The wait is not the City being slow. The wait is the number of times your package goes back and forth, and that number is set by how complete the first submission is.

The practical consequence: money spent making the first submission complete buys back weeks of calendar. An engineer who has done Toronto underpinning packages before, and who knows what this City asks for, is worth more than one who is cheaper by a few hundred dollars.

What the City's own data shows. We counted every Toronto underpinning building permit in the City's open data for our Toronto underpinning permits by ward study. For permits applied for in 2025, the median time from application to issuance was 13 days, 43% were issued within 10 days, and 18% took six weeks or more. So the 6 to 12 week experience is real, but it is the slow fifth of applications, usually the ones that went back for revisions, not the typical case. A complete package is what puts you in the fast majority.

What actually makes an underpinning application incomplete

These are the recurring gaps that send an underpinning package back, in rough order of how often they come up:

  • No sequencing plan, or a generic one. A drawing set that shows the finished condition but not the staged order of excavation and pour is the most common single omission. The sequence is the engineering.
  • Depths that do not reconcile with the survey. Proposed underside-of-footing elevations that do not tie to existing grade and existing footing elevations.
  • Missing shoring or excavation support details where the depth or the soil condition calls for them.
  • Nothing addressing the neighbouring foundation on a semi-detached or row house, where the adjacent structure is affected by the excavation.
  • Plumbing not included. Lowering a floor almost always means relocating drains below the new slab, and that is separate permitted work that is easiest to submit together.
  • An unsealed drawing set. A drawing prepared by an engineer but not sealed is not a sealed drawing.
  • Zoning conflicts surfaced late, most often where the lowered space is intended as a second suite and the proposal runs into a requirement the drawings never addressed.

Every item on that list is knowable before submission. That is the point: a review of six weeks or more is mostly a self-inflicted wound, and it is the one part of the timeline a homeowner can genuinely compress.

Semi-detached and row houses: the neighbour problem

On a semi or a row house the foundation you are underpinning is shared with, or immediately adjacent to, someone else's home. That changes the package. The drawings have to address what happens to the neighbouring foundation during excavation, and the sequencing becomes more constrained because you cannot open a section that undermines the party wall.

It also changes the human timeline. Access, notification and, in some cases, agreements with the neighbour sit outside the permit process but block the work just as effectively. Starting that conversation while the drawings are being prepared, rather than after the permit is issued, is what keeps the two tracks from running in series. Our semi-detached underpinning page goes into how the structural side differs.

Why the sequencing rule exists

The house does not stop being supported while its foundation is rebuilt. Underpinning works by excavating alternating sections, typically three to four feet wide, pouring each one, letting it cure, and only then moving to the adjacent section. The undisturbed sections carry the load while their neighbours are open.

Skipping or compressing that sequence is the failure mode that causes settlement, cracking and worse. It is also invisible to a homeowner watching from the top of the stairs, which is precisely why the sequence is specified on stamped drawings and verified by inspection.

What we do and do not do

We coordinate the permit process and work with licensed structural engineers who prepare and seal the drawings. We do not perform structural engineering ourselves and do not hold a professional engineering licence. The engineer's seal comes from the engineer, and their independence is a protection for you, not a formality. The closed permit and the engineer's reports are also what the next owner's lawyer will ask for, which is set out on buying an underpinned house in Toronto.

Common questions

Do I need a permit to underpin my basement in Toronto?

Yes. Underpinning alters the structural foundation, so a building permit is required. On top of that, the City requires a Professional Engineer's design and field review where the new footings go below a neighbouring building's footing within the soil's angle of repose (most semis, row houses and tight lots), where underpinning exceeds 1,200 mm of laterally unsupported height, or where the soil is clay or silt, and an engineer's testing and reports at the first and last stages on every underpinning job.

How much is the underpinning permit fee in Toronto?

Under the City fee schedule effective January 1, 2026, underpinning is charged at $12.37 per linear metre of wall being underpinned, and a minimum building permit fee of $214.79 applies to all work. For 100 to 140 feet of wall that is about $380 to $530; a longer perimeter, or other work on the same application such as a walkout or plumbing, adds to it. Contractors commonly quote permits and engineering together as a $2,000 to $3,000 combined line item.

How long does permit approval take?

In the City's own data, the median for 2025 underpinning permit applications was 13 days from application to issuance, and 18% took six weeks or more, usually after revisions. Add 1 to 3 weeks before that for the engineer's site visit and drawings, and plan on longer if the package goes back.

Is there a legal time limit on the City issuing a permit?

Yes, for a complete application. Ontario's Building Code sets the review timeframe for a house at 10 days, within which the municipality must issue the permit or refuse it with reasons. The reason real approvals take far longer is that the clock only runs once the application is complete, and incomplete submissions restart the process.

Why does my permit keep getting sent back?

Most often a missing or generic sequencing plan, depths that do not reconcile with the survey, absent shoring details, nothing addressing an adjacent foundation on a semi or row house, plumbing left out of the submission, or an unsealed drawing set.

Do I need a separate plumbing permit?

Lowering a basement floor normally means relocating drains below the new slab, which is separate permitted work. It is far easier to submit it alongside the building permit than to discover it afterwards.

Does underpinning a semi-detached house need anything extra?

The drawings have to address the neighbouring foundation and the sequencing is more constrained around the party wall. Access and notification with the neighbour sit outside the permit but can block the work just as effectively, so start that conversation while the drawings are in progress.

Can I underpin without a permit?

No. Beyond the safety issue, unpermitted structural work surfaces at resale, can void insurance coverage, and can trigger orders to remedy. It also removes the inspection process that protects you from a crew cutting corners on sequencing.

Who hires the engineer, me or the contractor?

Either arrangement is common. What matters is that the engineer is licensed in Ontario, seals the drawings, and is available for the staged inspections.

What happens during inspections?

A City inspector, and often the engineer, verifies the work at defined stages, checking that the sequence, depths and reinforcement match the approved drawings. Failing an inspection stops work until it is corrected.

Does benching need a permit too?

Yes. Bench footing is also structural foundation work requiring a building permit and proper drawings, even though the original footing is left undisturbed. Confirm with your engineer and the City whether your lot needs a sealed design.

Rather just talk?

(289) 207-6470

Tell us your basement perimeter and current ceiling height and we can give you a realistic range on the call.

  • A firm, itemized price up front
  • Permits and engineering in the number
  • The real timeline, honestly
Call now

Get a real range

Not a brochure. Tell us the basics and we will come back with numbers that reflect your actual foundation.

No obligation. Your details go only to our Toronto team.

Know the number before you dig.

Tell us your perimeter and current height. We will give you a realistic range, not a brochure.

Call (289) 207-6470
Call nowGet a range